Bar configuration
Specify solid or hollow construction, diameter, thread or surface geometry, length and any coupler arrangement. Each construction needs its own qualification.
Specify solid or hollow construction, diameter, thread or surface geometry, length and any coupler arrangement. Each construction needs its own qualification.
Nut, plate, washer and connection details must match the bar and required installation procedure. Assess the full assembly capacity.
Identify cementitious grout or resin cartridge, borehole geometry, installation equipment, cure conditions and acceptance testing.
A new section needs its own die: 4–8 weeks to make it and 6–10 weeks from an approved drawing to first delivery. The minimum order is 1,000 m per section. Samples are priced to the request, and the buyer pays the freight.
CHECK 1
Evaluate tensile rupture, bar shear across joints or bedding planes, thread stripping, plate bearing, bond failure and displacement. The nominal tensile strength of a bar alone is insufficient to specify the anchor.
CHECK 2
State service duration, sustained load, groundwater chemistry and temperature. For permanent support, expect a sustained-stress limit well below the short-term tensile strength and request creep-rupture evidence (ASTM D7337/D7337M) for the offered bar.
CHECK 3
The responsible ground-support designer defines the support pattern and acceptance tests. Cut-through behavior, mine fire requirements and other special conditions require project-specific confirmation.
Only a qualified ground-support design can establish suitability. A concrete reinforcing bar does not automatically include the thread, nut, plate and bond performance needed for a rock-bolt assembly.
No. The tunnel designer and equipment requirements determine acceptability. Submit the cutting, load, installation and testing requirements with the inquiry.
Custom profile development →Review available product evidence →
Start with a drawing and the intended use. These details help define the proposed supply package and qualification plan. We reply within one business day; a formal quotation follows once the specification and delivery are reviewed.