Tower Bridge is the gold lift bridge that frames Sacramento's riverfront. Built in 1935, it also holds a less visible first: its widened sidewalks over the lift span are made of fiber-reinforced polymer (FRP), because a concrete deck would have been too heavy for the machinery that raises the span.
Editorial note: F1 Composite had no role in this project. The facts below come from Caltrans and other public sources listed at the end.
The bridge
| Item | Value |
|---|---|
| Type | Vertical lift bridge |
| River | Sacramento River, between Sacramento and West Sacramento |
| Dedicated | 15 December 1935 |
| Route | State Route 275 (formerly US 40 and US 99W) |
| Total length | About 737 ft over eight spans |
| Lift span | 209 ft 6 in (Span 6) |
| Towers | 160 ft |
| National Register | Listed 1982 |
| Color | Gold since 2002 (silver at first, yellow-ochre from 1976) |
Trains crossed until 1962 and the tracks were removed in 1963. Today the bridge carries cars, bicycles and pedestrians, and it still lifts for river traffic. Caltrans calls it the first vertical lift bridge in the California highway system.
Why the sidewalks became FRP
In the 2000s, Caltrans and the cities of Sacramento and West Sacramento set out to widen the narrow walkways. The original sidewalk on the truss spans was about 4 ft wide; the project's environmental document gives the new width as 10 ft on the fixed and lift spans and 8 ft on the approaches.
The limit was the lift span. A movable span is balanced by counterweights, and its machinery is sized for a known weight. Adding wider concrete sidewalks would have added weight the hoist system could not take. The design team therefore replaced the whole concrete sidewalk deck on the lift span with a fiber-reinforced polymer deck. The Caltrans presentation compares the two: about 42 psf for a 5 in lightweight concrete deck against about 13 psf for a 5 in FRP deck.
Only the lift span received FRP. The fixed truss spans and the approaches kept lightweight concrete decks.
How the FRP deck was built
According to the Caltrans and city presentation:
- The deck panels were a patented FRP system with a trapezoidal tube core, spanning across the sidewalk between steel stringers.
- Typical panels were about 13 ft 6 in wide and 8 ft long, spliced in the field.
- Panels were fixed with threaded studs welded to the stringers, nuts and oversized washers; FRP cover plates sealed the access holes and FRP strips covered the bond lines.
- The deck was sanded in the shop and given a polymer concrete overlay in the field for wear and slip resistance.
- Historic light posts and railings were reused, and a reinforced concrete curb was cast on the FRP deck.
Because the lift span had to stay balanced, the contractor locked it with a temporary counterweight system during construction and added balance blocks as material went on.
Project team and dates
Caltrans led the project with the City of Sacramento and the City of West Sacramento. The presentation credits Parsons Brinckerhoff with design, Golden State Bridge as contractor and Martin Marietta Composites as fabricator and installer of the FRP deck. Construction started in December 2006 and the widened sidewalks opened in December 2007; some later company sources give 2008, the year the project began collecting awards. The project received the 2008 ASCE Region 9 History and Heritage Project of the Year and Engineering News-Record California's Best of 2008.
What the project shows about FRP decks
Tower Bridge is a clear case for composite decks: when the structure underneath has no spare capacity, cutting dead load is the only way to add width or use. The same reasoning drives FRP decks on movable bridges, historic trusses and pedestrian crossings. F1 Composite makes structural FRP deck panels and profiles for FRP pedestrian bridges; each project still needs a bridge engineer's design for loads, deflection, vibration and connections.
Tower Bridge Sacramento questions
When was Tower Bridge in Sacramento built?
It was dedicated on 15 December 1935 as the first vertical lift bridge in California's state highway system. It links Sacramento and West Sacramento across the Sacramento River and carries State Route 275.
Why is Tower Bridge gold?
It was first painted silver, then yellow-ochre in 1976 to match the State Capitol, and gold in 2002 after a public vote.
Why was FRP used for the Tower Bridge sidewalks?
The sidewalks were widened in 2007, and the lift machinery could not take added weight on the lift span. Caltrans replaced the concrete deck there with an FRP deck of about 13 psf, against 42 psf for 5 in of lightweight concrete.
Does the whole bridge have FRP sidewalks?
No. According to the Caltrans presentation, only the 209 ft lift span received the FRP deck; the fixed truss and approach spans use lightweight concrete.
Can you walk across Tower Bridge?
Yes. It carries cars, bicycles and pedestrians, with sidewalks on both sides.